We recently carried out a crane lift at Brassall Shopping Centre to replace a package A/C. Due to the position and size of the unit a Grove 130t All Terrain Slew Crane was required.
We decommissioned the package unit and removed the refrigerant as per Australian Standards. Then split the ductwork from the unit and removed electrics. The crane removed the unit and the old ductwork to make room for the new.
The new unit was then craned into place. As you can see, the support crane lifted the new ductwork into place while the 130t was setting up. The ductwork was then assembled and the final site measurements taken.
We are now waiting for the final duct transitions before completing. Stay tuned for completion photos!