The BPQ Group Gateway Building, Surfers Paradise project included condenser water pump replacement and the installation of an additional new pump.
- Due to the location, the pumps had to be lifted onto the roof via the stairwell.
- The new pump was installed first along with piping and electrics, all while the system was in operation.
- The system was shut down after hours to swap over pumps.
- The existing pump was then replaced.
- All sensors were relocated to suit the new piping layout.