This cooling tower project was recently completed by our team in Bundall, Gold Coast.
- Rooftop plant room was removed the week prior.
- Cooling tower was drained and electrically isolated after close of business on a Friday.
- On the Saturday:
- Piping was cut and the old tower was removed craned out.
- New tower was craned into place in sections and built in place.
- A second condenser water pump was craned into position.
- New piping was installed to suit the new layout with check valves and metering points.
- Works completed on the Sunday included:
- Tower refilled and power reconnected.
- Tower tested for leaks and operation.
- All was ready for the building to operate as normal on the Monday morning.