This cooling tower project was recently completed by our team in Bundall, Gold Coast.

  • Rooftop plant room was removed the week prior.
  • Cooling tower was drained and electrically isolated after close of business on a Friday.
  • On the Saturday:
    • Piping was cut and the old tower was removed craned out.
    • New tower was craned into place in sections and built in place.
    • A second condenser water pump was craned into position.
    • New piping was installed to suit the new layout with check valves and metering points.
  • Works completed on the Sunday included:
    • Tower refilled and power reconnected.
    • Tower tested for leaks and operation.
  • All was ready for the building to operate as normal on the Monday morning.