This project on the Gold Coast involved a main system replacement on level 2 and 6. The existing units were past there life expectancy and were struggling to maintain the required airflows. The units were replaced during a weekend to reduce downtime.

  • The old units were shut down and decommissioned on a Friday late afternoon.
  • The old unit was dismantled in place and carried out in pieces.
  • The new units were installed and commissioned on a Monday morning.
  • The units were connected up to the BMS system which controls and displays full operation.