Our team replaced the existing rooftop package unit with a new Temperzone unit at this Gold Coast office building.

  • Ductwork was manufactured the week before.
  • Welders attended on Thursday and modified the steel frame.
  • Friday evening after the office had closed the unit was decommission and made safe.
  • Saturday morning the unit was craned off and the new Temperzone unit was craned on. The ductwork was fitted with the electrics and the controls were installed and the unit tested.
  • Monday we attended to ensure there were no issues with the start-up.